Timeline

PCTCP-timeline.png

 

 PROPOSED PROJECT TIMELINE*

 25-26 August 2022  Consultation for 2023 Works
including integrated art work and new parking options in front of Port Campbell Shopping
 September -
 November
 2022 

2022 works
Tregea Street and Morris Street

  • Footpath works (Morris Street)
  • Zebra crossing (Tregea Street)
  • New parking (Tregea Street)
  • Traffic calming (Morris Street)
 September - December 2022     2023 Works tender process
 8 August 2023  2023 Works tender contract awarded
 August -
 December  
 2023 
LOWER LORD STREET 

August-September: Site preparation works, remove existing infrastructure and install power / lighting
Late August-October: Install new drainage system
October-December: Install new deck, limestone walls, new concrete asphalt pavement, and landscaping.

FORESHORE
August-September: Site preparation works, remove existing infrastructure, irrigation works and install power / lighting.
13 September: Dying Norfolk Island Pine to be removed from foreshore
October-December: Install retaining walls, new footpaths and furniture, complete landscaping.

 November
 2024
 Project completed